Engineering for a sustainable future
A history of sustained growth; excelling in every endeavour
Innovative Delivery Models
We work with our clients to develop innovative delivery models that promote mutual trust.
Delivering industrial solutions
MORPOL has excuted medium to large EPC turnkey projects with capability of executing EPC projects
Engineering for a sustainable future
A history of sustained growth excelling, in every endeavour;We work with our clients to develop innovative delivery models.;MORPOL has executed medium to large EPC turnkey projects.
since 1968
WHO WE ARE
A leading EPC- engineering, procurement and construction to the Oil & Gas industry.
MORPOL has emerged as an EPC Contractor from medium to large EPC turnkey projects in Pipeline Construction. Brownfield & Greenfield oil and gas facilities, Water, Process and Power industries with capability of executing EPC projects.
800
Workforce
55
Years of Experience
30
Backlog
200
Major Projects
WHAT WE DO
Your EPC contractor
Wherever you are on your EPC journey, MORPOL has the expertise and experience to support.
Relationship with foreign principals and strategic alliances with local and international technical partners have helped in the growth and capacity development of core competencies.
since 1968
Experiences we've created
Olorunsogo 24” x 21km Gas Pipeline Project
The Group Executive Director, Gas, NNPC.
"The project which was due to be completed within 12 months, was completed within six to seven months by the contractor, Jaihind Morpol. Jaihind Morpol has been able to deploy the best expertise and materials to get a quality job done. The contractor broke the record as it achieved about 109 joints and welds per day, a feat, which is quite unprecedented in the industry and which made it possible to finish the job in record time of six months."
Carter Bridge Pipeline Reticulation Project
GMD Lagos State Water Corporation
"Am quite impressed with the ingenuity of MORPOL. I have forwarded pictures to the Governor on the ongoing work. Please keep up the momentum!"
Indorama 18” x 83KM Gas Pipeline Project
The Group Executive Director, IEFCL
“We are happy to note that the mainline Hydro Test has been successfully completed today. Please convey our hearty congratulations to the entire team of MORPOL-JAIHIND consortium who have contributed for this gr8 milestone."
Gbaran Infill Project Package 2
SPDC Vice President, Operated & JV Partners, 10th October, 2016.
“Many thanks for meeting me at Gbaran last week. I was tremendously impressed by MORPOL’s progress on the Infill project and your commitment to safety……”
Gbaran Infill Project Package 2
Project Lead /Contract Holder, 23rd May, 2017
“Dear …… MORPOL Project Executives, This is to extend SPDC’s PM’s thanks to you for the safe and successful delivery of Koroama SPUU and EPUs. Very Well Done.”
Gbaran Infill Project Package 2
PM, 23rd May, 2017
c. Gents, I am pleased to inform you that Koroama 10 and EPU02 were brought on stream yesterday 22/5 and today 23/5. With EPU02 on stream, we have achieved delivery of EPU development one year ahead of GIP promise of May 2018.“ I would like to thank the entire team – project, Commissioning, Asset, Wells, Development, CP, Finance, SP, Security, HSE and of course the Contractors DAEWOO and MORPOL for the safe delivery of this milestone under the very challenging conditions”